No. |
Name & Address of the Client |
Description |
Commencement Date |
Completion Date |
|
[+]
|
1 |
Contracto W.L.L., Qatar |
Piling Works for Al Jassasiya Guest House |
July 2009 |
August 2009 |
| |
Scope of work
-
12m
-
219
|
|
[+]
|
2 |
Qatar National Bank - Doha Qatar |
Installation of diaphragm wall, excavation, dewatering and piling works for Qatar National Bank Headquarters Tower Project at West Bay - Doha |
July 2008 |
July 2009 |
| |
Scope of work
-
KEO International Consultants
-
18,000m2
-
550m
-
22m
-
18m
-
291,000m3
-
4m
-
22m
-
14m,24-36m,24-46m
-
60,172,337
|
|
[+]
|
3 |
Qatari Diar Real Estate investment Company |
Installation of diaphragm wall,excavation, dewatering and piling works for Doha Convention Center & Tower Project at West Bay |
May 2007 |
November 2008 |
| |
Scope of work
-
Hyder Consulting Middle Est
-
125,912m2
-
1,600m
-
12m - 17m
-
8m - 12m
-
1,172,109m3
-
6m
-
12m
-
10.5m-15m,25m-34m
-
2,334
|
|
[+]
|
4 |
Energy City Qatar |
Installation of diaphragm wall, excavation, dewatering and piling works for The Energy City Project at Lusail |
November 2008 |
July 2009 |
| |
Scope of work
-
ABS International Consultants
-
25,000m2
-
565m
-
16m
-
11m
-
185,000m3
-
3m
-
11m
-
7m,5m,7m
-
77,175,20
|
|
[+]
|
5 |
United Development Company |
Piling works for Viva Bahriya VB-09 at The Pearl Qatar |
October 2008 |
March 2009 |
| |
Scope of work
-
Khatib & Aalami
-
8m-20m,15m-27m,14m-38m
-
418,248,428
|
|
[+]
|
6 |
Marbu Contracting Co. |
Piling works for Commercial Plaza car park project at West Bay |
May 2008 |
November 2008 |
| |
Scope of work
-
Projacs International
-
18m
-
1106
|
|
[+]
|
7 |
SNC-Lavalin International - Canada |
Piling works for Coke & Alumina Silos, Liquid Pitch Tank, Silo Tower and Transfer System for QATALUM Aluminum Plant at Mesaieed, Qatar |
April 2008 |
September 2008 |
| |
Scope of work
-
22-26m
-
1540
|
|
[+]
|
8 |
Qatari Diar Vinci Construction (QCS) |
Piling and excavation works for Lusail Marine District 3 story car parks (4 No.) |
September 2007 |
June 2008 |
| |
Scope of work
-
QDVC
-
10.6m
-
2088
|
|
[+]
|
9 |
Qatar Fuel Company - Woqod |
Installation of diaphragm wall,excavation,dewatering and piling works for Woqod Tower project at West Bay |
November 2007 |
March 2008 |
| |
Scope of work
-
Romatre Project Italian Consultants
-
3,500m2
-
238m
-
20m
-
16m
-
50,855m3
-
3m
-
6m
-
12m-14m,12m-14m
-
185,79
|
|
[+]
|
10 |
Dorrat Adoha |
Piling works for Viva Bahriya VB 11 & 17 at The Pearl Qatar |
November 2007 |
February 2008 |
| |
Scope of work
-
Erga Group
-
8m-20m,15m-27m,14m-38m
-
235,198,285
|
|
[+]
|
11 |
First Qatar Real Estate Developing Co. |
Piling works for Viva Bahriya VB-06 & 07 at The Pearl Qatar |
September 2007 |
February 2008 |
| |
Scope of work
-
Projacs International
-
10m-15m,20m,19m-25m
-
284,164,283
|
|
[+]
|
12 |
Iberdrola Ingenieria y Construction |
Piling works for Mesaieed \"A\" 2000 MW CCPP Project |
July 2007 |
November 2007 |
| |
Scope of work
-
Iberdrola Ingenieria
-
21m,22m
-
545,415
-
142T,393T
|
|
[+]
|
13 |
Dorrat Adoha |
Piling works for Viva Bahriya VB-03,04&05 at The Pearl Qatar |
September 2007 |
November 2007 |
| |
Scope of work
-
Erga Group
-
8m-20m,15m-27m,14m-38m
-
418,248,426
|
|
[+]
|
14 |
Salam Bounian |
Installation of diaphragm wall, excavation,dewatering and piling works for the Gate Development Project at West Bay |
October 2006 |
July 2007 |
| |
Scope of work
-
The Cansult
-
24,00m2
-
700m
-
18m-20m
-
13m-15m
-
254,641m3
-
4m
-
15m
-
6.5m-7.5m,10m
-
607,73
|
|
[+]
|
15 |
Qafco |
Piling works for LLDPE Qatofin project at Mesaieed |
October 2006 |
March 2007 |
| |
Scope of work
-
Snamprogetti - Italy
-
24m
-
207
-
340T
|