Rigid Inclusions at Rua Al Madinah Superblock 5
Ammico’s scope of work comprised the design and installation of ground improvement works using rigid inclusion columns as well as the excavation and rock wall demolishing works to enable the subsequent contractor for super structure works. The major elements of the works were as follows:
-Ground improvement area of 27,500 m2 for 18 towers
-Installation of 5506 rigid inclusions columns with 600 mm diameter and up to 21 m deep
-Excavation and disposal with a total volume of approximately 130,000 m3 in addition to 13,905 m3 rock demolishing and disposal.